Where work is carried out on a daywork basis and the records are submitted within the contractual time, what is the effect on the contractor's entitlement to payment if the architect or engineer declines to sign them?
Contractors submit daywork records on time and find them left unsigned. Whether that defeats payment turns on who then bears the burden of proof, and the answer favours the contractor who submitted in time.
Leaving submitted daywork records unsigned does not defeat the claim: where the records were submitted on time and not challenged, the onus shifts to the architect or engineer to prove them wrong, so the records stand for payment unless the employer can produce convincing evidence that they are inaccurate, as JDM Accord v Secretary of State shows
Leaving submitted daywork records unsigned does not defeat the claim. In JDM Accord Ltd v Secretary of State for the Environment, Food and Rural Affairs the contractor submitted time records on a time-recorded contract, but there was no representative on every site to agree them, and payment was refused for want of records signed by both parties. The judge held that, because the recorded time had not been challenged when the timesheets were submitted, the onus was on the paying party to prove the information wrong, and the timesheets stood without further proof of accuracy unless it could bring forward convincing evidence of inaccuracy. An architect or engineer who receives daywork records and leaves them unsigned therefore risks having to disprove them later or certify them in full. Where there is a real disagreement, it should be raised when the records are submitted, identifying precisely which hours are challenged, failing which the burden shifts to the employer.
| The risk | An unsigned, unchallenged record does not defeat the claim |
| Burden shifts | The paying party must prove the information wrong |
| The records stand | Unless convincing evidence of inaccuracy is produced |
| Challenge at the time | Dispute the hours at submission, with full particulars |
| JDM Accord | The unchallenged timesheets stood for payment |