Resource Records Navigator

SCCSISociety of Construction Claims Specialists International
Delay and Disruption Protocol, 2nd edition

Record review navigator

SCL Protocol Appendix B
Resource Records Navigator

Review whether labour, equipment and material availability can be traced to defined work areas and programme activities. The navigator records availability and gaps. It does not decide whether any record proves delay, disruption, causation, quantum or entitlement.

Resource Records5 review itemsAppendix B, sections 3.1-3.4
Completion0 of 5No review items entered.
Review priorityAwaitingThis is an SCCSI record-review priority, not a legal conclusion.
Next actionBegin reviewStart with the first record group and identify the controlled location of each record.
01

Labour, equipment and material records

Check whether daily allocations, equipment status and material availability are recorded at a usable level of detail.

Source: Appendix B, sections 3.2 to 3.4, printed pages 74-75

Daily labour allocation

Record the work area used by each labour resource and relate the allocation to the relevant programme activity at a suitable level.

Status

Daily equipment allocation

Record where each item of equipment worked and relate that allocation to the relevant programme activity at a suitable level.

Status

Equipment operating status

State whether equipment was active or inactive and record the reason for any inactivity.

Status

Shared equipment availability

Identify shared equipment and record the hours for which it was available.

Status

Principal material delivery log

Record deliveries and the quantities of principal materials available for use in the works.

Status

This is a training aid. It does not give legal advice, and it does not assess admissibility, evidential weight or contractual compliance.

SCCSI | Construction claims training aid