Review whether the project record contains the programme material identified in Appendix B. The navigator records availability and gaps. It does not decide whether any record proves delay, disruption, causation or entitlement.

Programme records21 review itemsAppendix B, sections 1.1-1.4
Completion0 of 21No review items entered.
Review priorityAwaitingThis is an SCCSI record-review priority, not a legal conclusion.
Next actionBegin reviewStart with the programme set and identify the controlled location of each record.
01

The programme set

Check that the project file preserves each programme used to establish, accept, update or revise the planned route through the works.

Source: Appendix B, sections 1.1 and 1.2, printed page 72

Tender programme

Retain the programme issued with, or forming part of, the Contractor's tender record.

Status

Programme submitted for acceptance

Retain each proposed programme sent to the contract administrator for acceptance.

Status

Accepted Programme

Identify the programme that acquired accepted status under the project procedure.

Status

Updated Programmes

Preserve every update, including the final update that records the completed sequence.

Status

Proposed revised programmes

Keep each proposed revision, including submissions that were not accepted or adopted.

Status

Short-term look-ahead programmes

Retain the detailed near-term programmes used to direct and monitor forthcoming work.

Status

Internal target programmes

Keep the Contractor's internal target programmes in the project record.

Status

This is a training aid. It does not give legal advice, and it does not assess admissibility, evidential weight or contractual compliance.