Employer delay and later adverse weather

SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Legal and contractual solutions · Loss and expense

Can a contractor recover the cost of adverse weather encountered because earlier employer delay shifted the work?

But-for sequence, remoteness and broken causal chains

Potentially. The contractor must prove that the employer-risk delay moved the affected work into the adverse-weather period and that the later time and cost were a recoverable consequence under the contract and ordinary damages principles.

Quick answer

Recovery may follow where the employer delay materially caused exposure to the later weather and the causal chain remains intact

Compare the planned no-delay sequence with the actual sequence. Show that the work would probably have avoided the adverse conditions but for the employer event, that the weather then caused the claimed productivity or delay effect, and that this type of consequence was within the recoverable range. Remove normal seasonal allowance, contractor delay, defective planning and other intervening causes. A time-only weather clause does not automatically exclude damages caused by a separate earlier employer's breach, but the contract may allocate the risk expressly.

IssuePosition
Earlier employer-risk eventMust be proved and causally effective
Shift into weather periodDemonstrate through programme and weather evidence
Weather effectProve activity-specific time and productivity loss
Intervening causeMay reduce or break the causal chain
Contract risk allocationMay preserve, limit or exclude financial recovery

The rest of this solution is for members

Fifty of the two hundred contractual solutions are free to read. This is one of the remaining hundred and fifty, which Premium and Pro carry.

See what Premium includesAlready a member? Sign in