Late or second defects schedule

SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Legal and contractual solutions · Practical completion and defects

Must a contractor remedy defects omitted from the original defects schedule?

Defects procedures, continuing breach liability and limitation

Omission from the first schedule does not ordinarily extinguish liability for defective work. It may, however, affect the contractual right to require the contractor to return, the recoverable remedial cost and the administration of the defects procedure.

Quick answer

The underlying liability usually remains, but the contractual remedy and recoverable cost require separate analysis

A defects clause commonly gives the contractor an opportunity to correct notified defects; it does not, without clear wording, release liability for defective work omitted from a schedule or notified late. The employer may therefore retain a damages claim, subject to proof, causation, mitigation and limitation. If the employer bypasses the contractual opportunity to remedy, recoverable cost may be restricted. The contractor should inspect and offer a proportionate remedy while reserving any entitlement caused by fragmented or late notification.

IssuePosition
Defect omitted from first listLiability not automatically waived
Late second scheduleCheck contractual correction machinery
Underlying breach claimMay continue despite expiry of defects period
Denied opportunity to remedyMay affect recoverable cost
LimitationRuns from the legally relevant cause of action
Section 1

Separate procedure from liability

The contractual correction period regulates how defects are notified and remedied. The underlying obligation to comply with the contract is separate. Clear release or exclusivity wording is required before the procedure is treated as extinguishing an accrued damages claim.

Section 2

Questions for the second schedule

QuestionRequired analysis
Is the item defective?Compare the work with the contractual standard.
When was it discovered?Record whether it was patent or latent and when knowledge arose.
Was it omitted earlier?Identify what the first inspection could reasonably reveal.
Is return required?Apply the exact notice and correction provisions.
What loss follows?Prove reasonable remedial cost and consequential loss.
Is the claim in time?Identify cause of action and applicable statutory period.
Section 3

HW Nevill

HW Nevill (Sunblest) Ltd v William Press & Son Ltd(1981) 20 BLR 78

Defective construction is a breach capable of supporting damages. The defects procedure does not by itself replace that underlying contractual liability.

Section 4

Pearce and High

Pearce and High Ltd v Baxter1999

Damages remained recoverable for known defects omitted from the defects list. The omission did not waive the employer's underlying rights.

Section 5

A late list is not an automatic release

Failure to issue a schedule within the stated administrative period does not necessarily release the contractor from breach. It may prevent or alter use of the correction procedure, depending on the words used, without eliminating a separate claim for damages.

Section 6

Contractor's opportunity to remedy

The correction clause commonly benefits both parties by allowing the original contractor to return at lower cost. An employer that proceeds directly to a replacement contractor without allowing the agreed opportunity may face an argument that the additional cost was avoidable.

Preserve the position in writing

The contractor can offer inspection and correction without admitting liability, while recording any extra mobilisation cost caused by a fragmented schedule.

Section 7

Limitation Act 1980

For an action founded on simple contract, section 5 provides a six-year period from accrual of the cause of action. Section 8 addresses actions on a specialty and provides a twelve-year period, subject to its terms. Practical completion is not a universal statutory starting date. Identify when the pleaded breach and cause of action accrued, and consider any other applicable statutory regime.

Section 8

Do not confuse the defects period with limitation

A twelve-month or two-year correction period is not normally a contractual limitation period. Expiry may end the particular return-and-remedy machinery while leaving accrued contractual remedies available within the applicable legal time limit.

Section 9

Employer administration

Inspect methodically before the correction period expires, issue one supported schedule where possible and notify later-discovered items promptly. Give access and a reasonable correction opportunity unless the contract, urgency, safety or prior refusal justifies another course.

Section 10

Contractor response

For each later item, state whether liability is accepted, request access, propose the method and programme, and reserve the effect of late or duplicate mobilisation. Do not refuse every later item merely because it was absent from the first schedule.

Section 11

Decision sequence

1

Verify the contractual standard and alleged defect.

2

Read the schedule timing and correction provisions.

3

Identify why the item was omitted and when it was discovered.

4

Determine whether the contractual return right remains available.

5

Offer or permit inspection and proportionate correction.

6

Assess mitigation and any extra cost caused by late notice.

7

Identify accrual and the applicable limitation period.

8

Record agreement, refusal and completed remedial work.

Section 12

Authorities

AuthorityYear or statusWhat it decides
HW Nevill (Sunblest) Ltd v William Press & Son Ltd(1981) 20 BLR 78Defective construction may constitute breach supporting damages.
Pearce and High Ltd v Baxter1999Omission of known defects from the schedule did not extinguish the recorded damages claim.
Limitation Act 1980, section 5Current statuteSix years for an action founded on simple contract from accrual of the cause of action.
Limitation Act 1980, section 8Current statuteTwelve years for an action on a specialty, subject to the statutory wording.
Build your expertise in defects procedures, remedies and construction contract administration with SCCSI. sccsinternational.org
Note
This page states the position on the authorities listed as at 13 July 2026. Enforceability depends on the clause, contractual setting, facts and applicable law. This material is provided for educational and professional development purposes only and does not constitute legal advice. Always consult qualified professionals before acting. SCCSI and its contributors accept no liability for reliance on this material.