Oral construction contracts and adjudication

SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Legal and contractual solutions · Adjudication

Does statutory adjudication apply to an oral or partly written construction contract?

Repeal of section 107, applicable dates and proof of contractual terms

For construction contracts within the amended legislation in England and Wales, statutory adjudication is no longer confined to contracts made or evidenced in writing. Oral and partly written agreements can qualify, although proving their terms may be difficult.

Quick answer

Yes for contracts governed by the post-1 October 2011 regime, subject to statutory scope and proof of the agreement

Section 139 of the 2009 Act repealed section 107 of the 1996 Act. In England and Wales, the change applies to construction contracts entered into on or after 1 October 2011. The adjudication provisions themselves must meet the statutory written requirements; otherwise the Scheme supplies the procedure. The adjudicator may decide disputes about whether a contract exists and what its terms are, using documents, witness evidence and conduct. Historic contracts require the former writing rules to be checked.

IssuePosition
Contract from 1 October 2011Oral or partly written agreement may qualify
Earlier contractHistoric section 107 rules may apply
Adjudication procedure deficientScheme provisions may be imported
Oral terms disputedEvidence and witness credibility become central
Statutory scopeContract and operations must still qualify
Section 1

Current position in England and Wales

The statutory right is not lost merely because the construction contract was made orally or contains oral terms. The party relying on adjudication must still establish a qualifying construction contract, a crystallised dispute and compliance with the applicable procedure.

Section 2

The statutory amendment

Section 139 of the 2009 Act repealed section 107 of the 1996 Act. The amended regime applies in England and Wales to contracts entered into on or after 1 October 2011. The full statutory titles and official text are given in the authorities table.

Section 3

What still needs writing

The contract's adjudication procedure must include the required provisions in writing. Where it does not, the relevant Scheme procedure applies. Repeal of section 107 did not remove every written procedural requirement.

Oral contracts are permitted, not advisable

A statutory right to adjudicate does not cure uncertainty over scope, price, programme, notices or payment terms. Record the bargain promptly.

Section 4

Historic contracts

SituationRequired analysis
Before the amendment appliesCheck former section 107 and the governing commencement provisions.
Wholly written agreementHistoric statutory jurisdiction may be established.
Partly oral agreementFormer law may exclude statutory adjudication if material terms were not evidenced as required.
Implied price termHistoric outcome depends on the recorded agreement and applicable authority.
Later oral variationCheck the contract date and former jurisdictional rules separately.
Section 5

RJT Consulting Engineers

RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd[2002] EWCA Civ 270

The Court of Appeal took a strict approach: for the former section 107 the agreement itself, rather than merely evidence that some contract existed, had to be recorded in writing.

Section 6

Carillion and Rok

Rok Building v Bestwood Carpentry[2010] EWHC 1409 (TCC)

A distinction was drawn between a written price mechanism or implied reasonable-price term and an agreed oral price whose details were not recorded. That former section 107 analysis does not govern a post-amendment contract.

Section 7

Proving an oral agreement

EvidencePurpose
Witness evidenceWho agreed what, when, where and with what authority.
Contemporaneous documentsQuotations, messages, minutes, invoices and instructions.
PerformanceWork undertaken and accepted in accordance with alleged terms.
PaymentsRates, descriptions and payment conduct.
Subsequent statementsAdmissions or disputes about the bargain.
Implied termsTerms supplied by law only where the legal test is met.
Section 8

Adjudicator's procedure

The adjudicator can seek witness statements, contemporaneous records, focused submissions and, where fairness requires, oral evidence or a meeting. The timetable remains short, so the parties should isolate the disputed term and its evidential basis early.

Section 9

Existence and terms are jurisdictionally important

A party may dispute that any contract was concluded, that the responding entity was a party or that the work fell within the alleged agreement. The adjudicator must address those threshold issues while observing any properly reserved jurisdictional objection.

Section 10

Record formation after the event

Preserve quotations, purchase orders, emails, messaging records, meeting minutes, invoices, payment history, site instructions and evidence of performance. Do not create retrospective documents that purport to be contemporaneous.

Section 11

Pre-referral sequence

1

Identify the contract date and governing territorial regime.

2

Establish the parties, work, consideration and intention to contract.

3

Separate written, oral and implied terms.

4

Check statutory construction-contract and operation requirements.

5

Identify the adjudication procedure or imported Scheme terms.

6

Prepare witness and contemporaneous evidence of disputed terms.

7

Crystallise the contractual dispute.

8

Reserve and address any jurisdictional objection precisely.

Section 12

Authorities

AuthorityYear or statusWhat it decides
RJT Consulting Engineers Ltd v DM Engineering (Northern Ireland) Ltd[2002] EWCA Civ 270The former section 107 strictly required the agreement to be evidenced in writing.
Carillion Construction Ltd v Devonport Royal Dockyard2003The former writing requirement was applied to material contractual terms.
Rok Building Ltd v Bestwood Carpentry Ltd[2010] EWHC 1409 (TCC)This was the treatment of an unrecorded agreed price under the former provision.
Local Democracy, Economic Development and Construction Act 2009, section 139Current statuteRepealed the former section 107 writing restriction.
Build your expertise in oral contracts, adjudication and construction contract evidence with SCCSI. sccsinternational.org
Note
This page states the position on the authorities listed as at 13 July 2026. Enforceability depends on the clause, contractual setting, facts and applicable law. This material is provided for educational and professional development purposes only and does not constitute legal advice. Always consult qualified professionals before acting. SCCSI and its contributors accept no liability for reliance on this material.