Technology and Construction Court

GMC Utilities Group Ltd v Sumitomo Electric Industries Ltd

Neutral Citation: [2026] EWHC 885 (TCC)

JudgeMr Simon Lofthouse KC (sitting as a Deputy High Court Judge)
Judgment16 April 2026
JurisdictionEngland & Wales
ClaimantGMC Utilities Group Ltd
DefendantSumitomo Electric Industries Ltd

Summary

After a main contractor called on a performance bond given by its subcontractor, the parties agreed to place the disputed sum in an escrow account pending resolution of the claims. Their agreement, recorded in a letter of 8 November 2024, set out how and when the escrow money would be released, including a step the subcontractor had to take by 7 March 2025.

The dispute was whether the subcontractor had taken that step. It had issued court proceedings on 5 March 2025. The main contractor said that only arbitration would satisfy the agreement, so that the deadline had been missed and it was entitled to the escrow money. The subcontractor sought declarations the other way.

Mr Simon Lofthouse KC held that issuing the court proceedings satisfied the agreement. The escrow sum did not become payable to the main contractor and remained in the escrow account, though the court proceedings themselves were stayed to arbitration under the subcontract.

Background and facts

The main contractor was building an undersea electricity interconnector between Wales and Ireland and had subcontracted the onshore cable installation and associated civil works. After a dispute about the date of taking over and delay damages, the main contractor demanded payment under a performance bond given by the subcontractor.

To avoid payment out under the bond, the parties agreed that the sum would instead be paid into an escrow account pending resolution of the claims. Their agreement of 8 November 2024 provided for the escrow money to be released on agreement between the parties or on a decision of an adjudicator, a court or a competent arbitral tribunal, and required the subcontractor to commence proceedings on the claims by 7 March 2025.

The issue

The question was whether the subcontractor, by issuing court proceedings under Part 7 on 5 March 2025, had satisfied the requirement in the agreement, or whether, as the main contractor argued, only the commencement of arbitration would do, so that the deadline had passed and the escrow sum fell to be paid to the main contractor.

The decision

Mr Simon Lofthouse KC construed the agreement and held that court proceedings sufficed. The release mechanism referred to a decision of an adjudicator, a court or an arbitral tribunal, which showed that satisfaction of the step was not confined to arbitration, and the escrow agreement itself anticipated release on an order from any of those bodies. If the main contractor wanted the court to determine the claims, it could simply let the proceedings continue rather than seek a stay under section 9 of the Arbitration Act 1996:

"in issuing its Part 7 proceedings, on 5 March 2025 GMC has complied with the provisions of numbered paragraph 6 of the letter of 8 November 2024 with the effect that the Escrow Sum does not become payable to SEI under the provisions of that paragraph."Mr Simon Lofthouse KC, paragraph 64

He therefore rejected the main contractor's case that it was entitled to be paid the escrow sum, and the subcontractor's own declarations, which had been framed on the assumption that it had failed to comply, fell away because it had in fact complied. A paragraph of a witness statement was struck out, and an argument that the main contractor was estopped from denying compliance was addressed but did not need to be decided. The judge summarised the effect:

"GMC, having satisfied the requirements of paragraph 6 of the letter of 8 November 2024 by issuing Part 7 proceedings on 5 March 2025, the Escrow Sum remains in the Escrow Account on the applications before me."Mr Simon Lofthouse KC, paragraph 98

The Part 7 proceedings were then stayed to arbitration in accordance with the subcontract, so that the substantive claims would be arbitrated while the escrow money stayed in place.

Practical implications

Escrow release mechanics turn on the exact drafting. Where a bond demand is compromised by paying the sum into escrow, the conditions for release should be spelt out precisely. A clause that refers to a decision of an adjudicator, a court or an arbitral tribunal will not usually be read to confine a party to one of those routes.

Issuing court proceedings can satisfy a contractual deadline even where the dispute is arbitrable. A requirement to commence proceedings by a date can be met by issuing a Part 7 claim, notwithstanding an arbitration clause. The existence of the arbitration agreement goes to where the dispute is ultimately resolved, not to whether the deadline was met.

A stay to arbitration does not undo the step already taken. Proceedings issued to meet a contractual deadline can still be stayed to arbitration under the subcontract. The claimant keeps the benefit of having complied in time, while the substantive dispute proceeds in the agreed forum.

A party's own earlier correspondence may undercut its later case. The main contractor's solicitors had earlier described release as available on an order of a court as well as an arbitral tribunal. Parties should keep their correspondence consistent with the position they may later need to argue.

Practice points

  1. Set out escrow release conditions precisely; a clause referring to a decision of an adjudicator, court or arbitral tribunal will not usually be confined to arbitration alone.
  2. Issuing a Part 7 claim can satisfy a contractual requirement to commence proceedings by a deadline, even where the dispute is subject to arbitration.
  3. Proceedings issued to meet a deadline can still be stayed to arbitration; the claimant retains the benefit of timely compliance while the merits are arbitrated.
  4. Keep pre-action correspondence consistent; earlier statements about how a mechanism operates may be used against a party that later argues the opposite.