CR Construction (UK) Company Limited v Barclays Bank Plc [2026] EWHC 202 (TCC) Knowledge Check

SCCSI
(Providing Elite Certification Programmes to Construction Professionals Since 2009)
Explore Our Construction Claims and Contracts Certification Programmes
Presented by
Society of Construction Claims
Specialists International
sccsinternational.org
CR Construction (UK) Company Limited v Barclays Bank Plc
[2026] EWHC 202 (TCC) | Technology and Construction Court, Manchester
Before His Honour Judge Stephen Davies | Heard 29 January 2026 | Handed down 4 February 2026
Knowledge Check
Interim injunctions, performance bonds and certified demands

This Knowledge Check examines CR Construction's application to restrain Barclays Bank from paying Northern Gateway under a performance bond. The employer had demanded GBP 2,475,441.02 for liquidated damages, and CR Construction also sought an order requiring the bank to return money received under a counter-guarantee.

The application was made against the issuing bank, not the employer. CR Construction did not allege fraud. The court held that the wider ground available to restrain a beneficiary with no contractual right to call a bond did not provide the same route to an injunction against the bank.

The court also considered the bond wording, the employer's certificate, the demand's letterheading, discharge by alleged repudiatory breach, set-off, damages and balance of convenience. None of CR Construction's grounds amounted to a strong case, and the injunction was refused.

This Knowledge Check covers
  • The payment restraint and counter-guarantee relief sought
  • The distinction between injunctions against banks and beneficiaries
  • The amended JCT contract and performance bond
  • The effect of termination under clause 2.2 of the bond
  • The guarantee and net-liability wording in clause 5.1
  • The certificate requirements and conclusive-evidence provision
  • The Hong Kong counter-guarantee
  • The demand made for liquidated damages
  • The adequacy of the evidence of financial harm
  • The balance of convenience and refusal of relief
Choose your Knowledge Check mode
Legal Disclaimer
This Knowledge Check is provided for educational and professional development purposes only and does not constitute legal advice. The content reflects interpretations and analyses that may not apply to specific circumstances. Contract interpretation depends on specific wording, jurisdiction, and factual context. Always consult qualified legal professionals before making decisions based on this content. SCCSI and its contributors accept no liability for reliance on this material.