E & TL Jones (Civils) Ltd v Vale of Glamorgan Council
| Judge | His Honour Judge Keyser KC, sitting as a Judge of the High Court |
| Judgment | 4 August 2026 |
| Hearing | 7 July 2026 |
| Court | Technology and Construction Court (KBD), Business and Property Courts in Wales, Cardiff |
| Jurisdiction | England & Wales |
| Claimant | E & TL Jones (Civils) Ltd |
| Defendant | Vale of Glamorgan Council |
| Case reference | HT-2025-CDF-000009 |
Summary
The claimant was ISG's groundworks subcontractor on a school extension in Penarth. ISG's own contract with the council required a project bank account, the device that holds subcontractors' money on trust against a main contractor failure. That account was never opened. When ISG entered administration in September 2024, the subcontractor was left unpaid on a certified application for £486,017.67, with no realistic prospect of recovery in the administration.
It sued the council rather than ISG, contending that the council broke the main contract by paying ISG directly instead of into the account, and that it could enforce the payment clause against the council through the Contracts (Rights of Third Parties) Act 1999.
Judge Keyser KC dismissed the claim. It failed at the first step: the clause benefited Named Suppliers, a status the subcontractor never held. On assumptions he did not need to make, the judge added that there was no breach, no loss caused, and a waiver by ISG in taking the direct payments. The council won.
Background and facts
The council engaged ISG on 23 August 2023 under an amended NEC4 Engineering and Construction Contract, Option A, at a price of £20,897,221.77. Secondary Option Y(UK)1 required ISG to establish a project bank account with Santander within three weeks of the Contract Date. The Contract Data recorded "named suppliers are TBC". Under clause Y1.6, ISG had to propose each supplier for addition as a Named Supplier, and the supplier, the council and ISG would then sign a joining deed. ISG proposed nobody. Nobody signed.
The subcontract of 15 May 2024 was worth £2,950,574.69, some 14 per cent of the main contract price. The account itself sat with the bank, delayed first by mislaid paperwork and then by customer due diligence checks awaiting ISG's proposed sale. The sale collapsed, and ISG entered administration on 20 September 2024.
The council meanwhile paid ISG directly: seven certified payments between November 2023 and September 2024, the last including the £486,017.67 owed to the claimant on its fourth subcontract application. ISG never passed it on.
The issue
The subcontractor argued that clause Y1.8, which channels the client's payments into the account, purported to confer a benefit on it as a Supplier, so sections 1(1)(b) and 1(3) of the 1999 Act allowed it to enforce the clause. Had the council withheld the direct payments, it said, ISG would have opened the account and the money would have reached it on trust.
The council answered that the class benefited was Named Suppliers, which excluded the claimant; that nothing was breached because the account never existed; that the hold-up lay with the bank; and that ISG had in any event waived any breach.
The decision
The claim failed at the first hurdle: the judge held that the third parties on whom clause Y1.8 purported to confer a benefit were those admitted to the trust arrangements, and only them.
The relevant class of third party is Named Suppliers. The claimant was never a Named Supplier.His Honour Judge Keyser KC, paragraph 34
The subcontractor could not escape that by blaming the council.
To say that the claimant can circumvent section 1 in reliance on a breach of the clause sought to be enforced under section 1 is tantamount to saying that the claimant can enforce a contractual term without satisfying the requirements of the 1999 Act.His Honour Judge Keyser KC, paragraph 36
There was no breach in any event. Clause Y1.8 imposes a positive duty to pay into the account; it says nothing about payments made where no account exists.
But the obligation in Clause Y1.8 was a positive one, not a negative one, and it was impossible of performance, because it was premised on the existence of a PBA. The condition precedent to performance of the obligation in Clause Y1.8 had failed. Therefore the failure to pay into a PBA was not a breach of contract.His Honour Judge Keyser KC, paragraph 56
The judge went further, though he did not need to. With no account and no Named Suppliers, he considered the council obliged, or at the least entitled, to pay ISG directly, read with the payment machinery in clause 51. Causation failed too: the account was stuck at the bank and would not have opened before the administration whatever the council did. ISG had also applied for and accepted every payment, waiving any breach, a defence open to the council under section 3(2) of the 1999 Act. The claim was dismissed.
Practical implications
The danger is plain. A project bank account clause on paper is not money on trust. Until the account is open and the subcontractor has signed the joining deed, the trust never bites, and a subcontractor who assumed protection is unsecured when the main contractor fails.
The two steps are separate, and both matter. Joining does not wait for the account: the judge rejected the submission that a supplier could not be added until the account existed. A subcontractor can press for Named Supplier status from the first day of its subcontract.
For employers, the judge's view, which he did not need to reach, was that with no account and no Named Suppliers the council was obliged to pay ISG directly, or at the least permitted to. He held that the October 2020 amendments to Option Y(UK)1, which expressly allow direct payment where no account exists, say nothing about how the earlier wording is read.
Practice points
- Treat a project bank account clause as machinery, not protection. Ask two questions on appointment: is the account open, and am I a Named Supplier? If either answer is no, you are an unsecured creditor of the main contractor.
- Press for the joining deed at subcontract stage. Proposal, acceptance and execution under clause Y1.6 do not require the account to exist first, so nothing stops the paperwork being done on day one.
- Create the record early. The proposal sits in the contractor's hands, so demand in writing that you be put forward as a Named Supplier, and copy the project manager.
- Do not bank on the 1999 Act. The court read the benefited class from the contract's own definitions, and the class here was confined to those who had signed the joining deed.
- Employers should diarise the contractor's three-week deadline for establishing the account and chase it in writing, and should record the basis of any direct payment made while the account is pending.