Effect of adjudication provisions that do not comply with section 108

SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Legal and contractual solutions · Adjudication

What is the effect of contractual adjudication provisions that do not comply with section 108?

Mandatory requirements, displacement by the Scheme and incompatible late-decision clauses

Parties may agree their own adjudication procedure, but it must satisfy the mandatory requirements in section 108. If it does not, the statutory Scheme applies through section 108(5).

Quick answer

Audit the contractual procedure against every section 108 requirement; a material failure may displace the contractual adjudication machinery with the Scheme

Do not assume that an offending sentence can simply be replaced while the remainder of the contractual procedure survives. The authorities treated non-compliant timing provisions as causing the Scheme adjudication provisions to apply rather than allowing incompatible contract rules to coexist with selected Scheme terms. The result depends on the incorporated procedure and the defect identified. Map appointment, referral, timetable, extensions, binding effect and correction powers against the current statute before the notice is served.

IssuePosition
Contract procedure satisfies section 108Contractual rules govern
Mandatory requirement omitted or contradictedScheme may apply
Clause validates late decision indefinitelyNon-compliant timing risk
Attempted selective substitutionCheck authority before severing
Scheme appliesUse one coherent procedure