Are project managers under the NEC contract required to act impartially, or do they act as agents for the employer?

SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Legal and contractual solutions - Rights and remedies

Under the Engineering and Construction Contract (NEC), does a project manager performing contract functions owe a duty of impartiality, or does the project manager act solely as the employer's agent?

The NEC project manager, impartial certification and Sutcliffe v Thackrah

An architect must certify impartially. In Costain v Bechtel the court held it at least properly arguable that the same duty binds the project manager under the NEC form when issuing payment certificates, whatever its interest in the outturn, but expressly declined to decide the point on an interim application.

Quick answer

They must act impartially when certifying: Costain v Bechtel held it properly arguable that the Sutcliffe v Thackrah duty of impartial certification applies to a project manager under the NEC form on payment certificates, even where a pain-share or gain-share mechanism gives the project manager a financial interest in the outturn, though on functions such as design change it acts in the employer's interest

They must act impartially when certifying. Costain v Bechtel held it properly arguable that the principle in Sutcliffe v Thackrah, that a certifier must act impartially between employer and contractor, applies equally to a project manager under the NEC form: when issuing payment certificates the project manager must hold the balance fairly, even where a pain-share or gain-share mechanism gives it a financial interest in keeping the certified outturn down. That does not make the project manager impartial in everything: on functions such as changing the design it acts in the employer's interest, just as an architect acts as the employer's agent when issuing variations, but on certification it must be even-handed. In Costain the court refused an injunction, because it could not supervise the project manager, but it did not finally decide the point, and a contractor that doubts a certificate can use the contract's dispute-resolution mechanism.

The architect's dutySutcliffe v Thackrah: certify impartially
Extended to NECCostain v Bechtel: arguably the same duty binds the project manager
Payment certificatesHold the balance fairly, whatever the interest in outturn
Agent for some actsDesign change is in the employer's interest
No injunctionThe principle stood, but the court would not supervise it

The rest of this solution is for members

Fifty of the two hundred contractual solutions are free to read. This is one of the remaining hundred and fifty, which Premium and Pro carry.

See what Premium includesAlready a member? Sign in