Disruption evaluation and the measured mile

SCCSI
Presented by
Society of Construction Claims Specialists International
sccsinternational.org
Legal and contractual solutions · Loss and expense

How may disruption be evaluated, and what is the measured-mile method?

Productivity comparison, causal proof and alternative valuation

The measured mile compares productivity on substantially similar unimpacted and impacted work. It can quantify lost productivity, but it does not establish contractual entitlement or prove which event caused the difference.

Quick answer

Use a like-for-like productivity comparison after proving the compensable disrupting event and affected work

Select an unimpacted baseline from the same project where possible. Compare the same work type, method, crew skill, location and maturity, using consistent units and hours. Remove learning curve, weather, design, access and contractor-responsible differences. If no valid measured mile exists, use a modified comparison, event-specific additional-resource analysis, reliable industry data or a reasoned assessment. Tender productivity and total-cost approaches require particular caution.

IssuePosition
EntitlementIdentify compensable event and contractual route
Measured mileCompare like unimpacted and impacted productivity
CausationRemove non-compensable causes and confounding factors
Alternative analysisUse event-specific hours, external benchmarks or reasoned assessment
Global overspendDoes not by itself prove disruption loss
Section 1

Disruption is productivity loss

Disruption concerns inefficient use of resources, not merely delayed completion. The contractor must identify what work was performed, the resources used, the expected reasonable productivity and how a compensable event changed that productivity.

Section 2

Entitlement precedes measurement

A productivity comparison quantifies difference. It does not prove that the employer was responsible, that the event was compensable or that every difference resulted from it. Establish the causal event narrative first.

Do not claim the whole labour overrun

Separate tender error, learning curve, poor supervision, absenteeism, weather, access, rework and other contractor-risk causes before attributing loss.

Section 3

Measured-mile method

Calculate units completed per labour hour, or labour hours per unit, for a demonstrably unimpacted period and the impacted work. Apply the supported productivity difference to the comparable impacted quantity, then value the resulting lost hours under the contract.

Section 4

Comparability tests

TestRequirement
Work typeSame operation, specification and method.
ComplexityComparable geometry, interfaces and quality demands.
CrewSimilar size, skill, supervision and learning stage.
LocationComparable access, congestion and workface conditions.
Time conditionsAccount for season, weather, shifts and fatigue.
Other eventsRemove changes, defects and contractor inefficiency.
Section 5

Whittall Builders

Whittall Builders Co Ltd v Chester-le-Street District Council(1987) 40 BLR 82

Productivity during hindered dwelling work was compared with a later orderly period. The agreed production figures supported a practical percentage assessment of labour productivity loss.

Section 6

Alternative event-specific schedules

Where no clean baseline exists, isolate extra labour and plant hours by event and activity, compare them with a supported no-event requirement, and present the calculation in traceable schedules.

Section 7

Difficult quantum does not erase proven loss

Chaplin v Hicks[1911] 2 KB 786

A tribunal should make the best reasonable assessment where breach and actual loss are established but exact monetary measurement is difficult.

Penvidic Contracting Co Ltd v International Nickel Co of Canada Ltd(1975) 53 DLR (3d) 748

An estimated valuation was adopted where the owner's breaches caused loss but accurate proof of additional cost was impracticable.

Section 8

Cost-less-recovery risk

A labour-cost-over-tender approach may be substantially reduced where the evidence does not show that all the excess cost arose from the matters relied on, or where it reveals inefficient use of labour.

Section 9

Walter Lilly and causal proof

Walter Lilly & Company Ltd v Mackay[2012] EWHC 1773 (TCC)

The court addressed disruption and global claims, confirming that causation remains essential. A claimant is not automatically barred because precise allocation is difficult, but material contractor-responsible causes and evidential gaps affect recovery.

Section 10

Data and calculation

DataControl
QuantityInstalled units measured consistently.
HoursPaid and productive hours reconciled to payroll.
CrewTrade, skill, size and supervision.
ConditionsLocation, access, weather, design and sequence.
MaturityLearning curve and repetition stage.
EventsDates and activities affected by each compensable cause.
Section 11

Practical sequence

1

Define the compensable disruption events.

2

Map each event to affected activities and dates.

3

Select a genuinely comparable unimpacted baseline.

4

Normalise quantity, hours, crews and conditions.

5

Calculate productivity difference and lost hours.

6

Remove contractor-risk and other confounding causes.

7

Use alternative assessment only with disclosed assumptions and sensitivity checks.

Section 12

Authorities

AuthorityCitationWhat it decides
Whittall Builders Co Ltd v Chester-le-Street District Council(1987) 40 BLR 82A like-for-like project productivity comparison supported the recorded disruption award.
Chaplin v Hicks[1911] 2 KB 786Proven loss may be reasonably assessed despite measurement difficulty.
Penvidic Contracting Co Ltd v International Nickel Co of Canada Ltd(1975) 53 DLR (3d) 748Estimated damages were permitted where accurate proof was impracticable on the recorded facts.
Walter Lilly & Company Ltd v Mackay[2012] EWHC 1773 (TCC)Disruption recovery remained dependent on proof of causation despite allocation difficulty.
Build your expertise in disruption analysis, measured-mile evidence and construction claims with SCCSI. sccsinternational.org
Note
This page states the position on the authorities listed as at 13 July 2026. Enforceability depends on the clause, contractual setting, facts and applicable law. This material is provided for educational and professional development purposes only and does not constitute legal advice. Always consult qualified professionals before acting. SCCSI and its contributors accept no liability for reliance on this material.