Does approval or acceptance of a programme require information to be issued in accordance with its sequence?
Not necessarily. Programme approval does not, without supporting wording, replace the contract's information-release obligations. The executed contract determines when information is due and what role the programme plays.
Programme acceptance alone does not create an unrestricted duty to issue information solely to suit that programme
Read the programme clause, information schedule and request procedure together. The contractor should give adequate advance notice of the information required and show why the requested date is reasonable in all the circumstances. Progress and the accepted sequence may be relevant evidence, but the design team must also have reasonable production time and necessary inputs. Some contracts expressly give the accepted programme a stronger role; that effect must come from the wording.
| Issue | Position |
|---|---|
| Approved programme | May record intent without amending duties |
| Information release schedule | Express dates ordinarily govern |
| Contractor request | Should identify need date and reasonable lead time |
| Reasonable issue time | Assessed from all relevant circumstances |
| Express accepted-programme mechanism | May give programme contractual effect |