Case: United Utilities Water Limited v Northstone (NI) Limited (trading as Farrans Construction) [2026] EWHC 1057 (TCC)
Court: High Court of Justice, Business and Property Courts in Leeds, Technology and Construction Court (KBD)
Judge: Her Honour Judge Kelly sitting as a Judge of the High Court
Hearing Date: 24 June 2025
Judgment Date: 6 May 2026
Case No: HT-2025-LDS-000013 and HT-2025-LDS-000014
United Utilities Water Limited (UU) engaged a joint venture comprising Northstone (NI) Limited, trading as Farrans Construction, and Roadbridge Limited for the West Cumbria Supply Project. The works included 32 kilometres of raw water aqueduct and 24 kilometres of water mains under an amended NEC3 Engineering and Construction Contract. A payment assessment issued through CEMAR recorded a negative amount due of £3,269,328.05, and an adjudicator later ordered Farrans to pay that sum plus VAT. UU sought summary judgment to enforce the award, while Farrans brought a connected Part 8 claim challenging the payment notice and the asserted need for a pay less notice (paragraphs 1-2 and 14-23). The court had to decide whether Farrans' two issues could properly be determined on the evidence available in Part 8 proceedings (paragraphs 48-65).
Central Legal Test: The construction of a contractual payment notice is objective: the court asks how a reasonable recipient, circumstanced as the actual parties were, would have understood it in its factual and contractual context. The immediate question was whether the evidence permitted that assessment within Part 8 proceedings (paragraphs 27 and 48-63).
Enforcing claimant: United Utilities Water Limited, represented by Ms Jennie Gillies, instructed by Addleshaw Goddard LLP.
Defendant and Part 8 claimant: Northstone (NI) Limited, trading as Farrans Construction, represented by Mr William Webb KC, instructed by Brodies LLP.
Project: Contract 6 of the West Cumbria Supply Project, covering 32 kilometres of raw water aqueduct and 24 kilometres of network water mains (paragraphs 1, 3-5 and 43-44).
Original form: NEC3 Engineering and Construction Contract, April 2013, Option C with bespoke amendments, dated 30 March 2017, with Prices of £85m (paragraphs 4-5).
Later agreements: A settlement agreement dated 25 July 2018 increased the Prices to £95m. A Deed of Variation dated 30 September 2021 changed the pricing basis from Option C to Option A, introduced milestone payments and increased the Prices to £131.6m (paragraphs 9-12).
System: The parties used CEMAR to administer payment documents, although its automatically generated dates did not reflect the amended payment timetable (paragraphs 14 and 52).
The Project Manager issued PA-70 on 11 October 2024 in response to AFP77 and AFP78. It assessed minus £3,269,328.05 as due, based on Milestone 9 and a nil assessment for Milestone 11 (paragraphs 14-16 and 38). Farrans contended that PA-70 was invalid because CEMAR displayed 8 November 2024 as the due date, the document was unclear and a negative figure did not demand repayment. It also disputed any obligation to issue a pay less notice (paragraphs 21-23 and 31-40).