Premier Modular Limited (PML) sought summary judgment enforcing an adjudicator's re-corrected decision dated 26 February 2026 for £1,655,385.49 and other relief. The dispute arose under an NEC4 Option A contract for a new barn theatre at Maidstone Hospital. PML alleged that late provision of a permanent water supply caused delay and a compensation event. The adjudicator found for PML under clause 60.1(3) by treating an unaccepted revised programme as the Accepted Programme, although both parties had agreed that only the original contract programme had been accepted. The NHS Trust resisted enforcement on natural justice grounds, and the court dismissed PML's application because the adjudicator decided the central issue on a case neither party had advanced or had a proper opportunity to address (paragraphs 1-3 and 33-51).
The Trust said the decision was reached through obvious procedural unfairness. Its principal case was that the adjudicator invented a clause 60.1(3) route founded on an Accepted Programme which both parties agreed did not exist (paragraphs 2 and 35-43).
PML argued that the referred dispute and contractual materials were broad enough to permit the adjudicator's reasoning. It said the water-supply issue, clause 60.1(3) and programme status had been sufficiently canvassed, and that the adjudicator was not confined to choosing between the parties' submissions (paragraphs 37-41).