Darchem Engineering Limited sought summary judgment enforcing an adjudicator's decision for £23,944,012. The subcontract for specialist stainless-steel works at Hinkley Point C was made between two unincorporated joint ventures. Bouygues Travaux Publics and Laing O'Rourke formed the contractor joint venture, BYLOR; Darchem and Framatome Limited formed the subcontractor joint venture, EDEL. Darchem alone commenced three adjudications, stating that it acted jointly and severally as the Subcontractor. The defendants challenged jurisdiction because Darchem was not itself the defined contractual 'Party' entitled to use the adjudication clause. The court accepted that construction and refused enforcement (paragraphs 1-5 and 43).
BYLOR argued that the subcontract was bilateral: the defined Parties were the Contractor JV and the Subcontractor JV. Darchem was a constituent of EDEL but not itself a defined Party entitled to refer a dispute under Option W (paragraphs 14 and 16-20).
Darchem relied on the Agreement's naming of all four companies, the statement that all were together known as the 'Parties', their separate execution of the deed and wording that the JV members acted jointly and severally. It said these features made Darchem a Party able to adjudicate alone (paragraphs 15 and 21-37).